CoRoutines

Posted by Ben Michaud on December 18, 2009
I was reviewing the code for

vCoRoutineSchedule();

If I'm not mistaken, when a task makes a call to this routine and there is a coroutine available to run, that CoRoutine runs in the task's stack who made the call to vCoRoutineSchedule();??? Thanks for your time.

Ben

RE: CoRoutines

Posted by Dave on December 19, 2009
Yes that is correct. It is normal to run coroutines in the idle task.

RE: CoRoutines

Posted by Ben Michaud on December 19, 2009
Thanks for the confirmation!!!